Final Cost For New Waldens Ridge Fire Hall Comes In At $4,775,936

  • Wednesday, February 26, 2020

The final bill for a new fire hall at Walden came in at $4,775,936, officials said.

The County Commission is being asked to approve a cost overrun of $205,936.

Todd Leamon, county public works administrator, said there initially was no contingency built into the project.

He said extra expenses were caused by some rock and soils that were encountered, the requirement of a retaining wall to separate from a creek, and some communication items. 

Breaking News
I-40 Shut Down In Both Directions At Lenoir City Due To Multiple Fatalities Accident
  • 6/30/2025

I-40 was shut down Monday afternoon in both directions due to a multi-vehicle accident with multiple fatalities. Westbound lanes were shut down so that a patient could be transported by Lifestar. ... more

2 People Charged With Animal Cruelty After Live And Dead Animals Found In Deplorable Conditions
  • 6/30/2025

Two people face a host of charges in Walker County following the discovery of three deceased dogs and five others struggling to survive inside a hot business building. Warrants have been issued ... more

Man Who Fatally Shot, Beat Another Man At Public Housing Site Gets 18 Years
Man Who Fatally Shot, Beat Another Man At Public Housing Site Gets 18 Years
  • 6/30/2025

A man who fatally shot and beat another man at a public housing site has been sentenced to 18 years in state prison. Marvin Jermane Davis, 51, got six years for voluntary manslaughter and ... more