Weekly Road Construction Report

  • Thursday, March 23, 2023

Here is the weekly road construction report for District 29: 

BRADLEY COUNTY SR-40 (INMAN ST. S.E.) Utility Work both directions from LM 2.04 to LM 2.65: Nighttime police assisted detour on SR-40 (Inman Street) between Durkee Road SE to Bates Pike SE. Motorists should reduce speed and use caution while traveling through the work zone and be aware of construction personnel. Trucks, signage, cones/barrels, and flaggers will be present, 03/27/23 from 10 pm - 12:30 am with rain dates of 03/29/23 and 03/30/23. [2022-263]

 

BRADLEY COUNTY SR-40 (WATERLEVEL HWY.) Utility Work both directions from LM 1.3 to LM 2: Nighttime police assisted detour on SR-40 (Appalachian Hwy/APD-40) between McGrady Drive to Blackburn Rd SE. Motorists should reduce speed and use caution while traveling through the work zone and be aware of construction personnel. Trucks, signage, cones/barrels, and flaggers will be present, 03/28/23 from 10 pm - 2 am with rain dates of 03/29/23 and 03/30/23. [2022-263]

 

BRADLEY COUNTY SR-40 (WATERLEVEL HWY.) Utility Work westbound from LM 2.04 to LM 8.62: Shoulder and single lane closures from Hancock Road NE to Durkee Road NE. Motorists should reduce speed and be prepared to stop. Trucks, signage, drums/cones, and flaggers will be present, 02/23/23 through 03/29/23 from 9 am – 2 pm. [2022-263]

 

BRADLEY COUNTY SR-60 Utility Work both directions at LM 12.79: Nighttime police assisted traffic stoppage and ramp closings at the SR-60 and SR-40 interchange. Ramps will be closed temporarily between 20th St Benton Pike. Motorists should reduce speed and use caution while traveling through the work zone and be aware of construction personnel. Trucks, signage, cones/barrels, and flaggers will be present, 03/27/23 from 10 pm - 10:30 pm with rain dates of 03/29/23 and 03/30/23. [2022-263]

 

BRADLEY COUNTY SR-60 widening from the 4-lane north of I-75 (LM 17.2) to SR-306 (LM19.9): During this reporting period the contractor will have short term intermittent lane closures throughout the project for utility relocation and moving equipment as work continues on new roadway alignments and a new bridge over Candies Creek. The speed limit in the work zone has been reduced to 35 mph. Motorists are advised to use caution in the work zone and watch for flaggers assisting with traffic control.

[Summers-Taylor, Inc./Wagner/CNV130]

 

HAMILTON COUNTY I-24 interchange improvement at SR-2 (US-11, US-41, US-72, Broad Street) and SR-58 (Market Street): Williams Street is closed to all traffic at the I-24 underpass to support the installation of new storm drainage structures for the new frontage road. Traffic will still be able to access the ramps to I-24 and US-27, but no through traffic will be allowed on Williams Street between West 21st Street and West 25th Street. Traffic will detour around the closure via West 21st Street and Broad Street. Signs are posted. The contractor will be working on new bridge construction, storm drainage structures, and utility relocation. The US-27 N on-ramp at William St. has been closed and it will remain closed until the new alignment for this ramp is completed. There will be marked detour signs to use the Broad St. US-27 on-ramp. The contractor has opened up the new Broad St exit off I-24 and closed the existing exit to the Broad St that is off the US27 S exit. Traffic from US27 S that needs to access Broad St. will use the Williams St. exit. Detour signs are in place. Drivers need to be aware of the changes. The US 27 South ramp onto I-24 East will be reduced to two lanes with the Williams St. exit still open. This ramp will be this way for several months and traffic is advised to drive with caution in this area. During this reporting period, from 9 AM -3:30 PM, there will be a temporary lane shift on the Williams St. off ramp during this time period. On Sunday thru Tuesday (depending on weather) from 9 PM-6 AM, the contractor will be closing the Williams St Ramp off of the US27 S on Ramp to I24 E and the contractor will be opening up the new US27 S ramp to Broad St. Ramp. Traffic is advised to be cautious in this area and to pay attention to the new traffic pattern.

[Wright Brothers Construction Company, Inc./Curtis/CNU011]

 

HAMILTON COUNTY I-75 at I-24 Interchange Reconstruction Phase 2: Weather permitting, the contractor will implement single lane closures between the hours of 9 PM until 6 AM Sunday through Thursday, at following locations: I-24 WB MM 185 to MM 183 and North Terrace, I-75 NB MM 2 to MM 4, I-75 SB MM 4 to MM 2.

[Wright Brothers Construction Company, Inc./Maj Prj - Blevins/DB2101]

 

HAMILTON COUNTY SR-17 (BONNY OAKS DR.) Utility Work both directions from LM 8.25 to LM 9: Mobile shoulder and lane closures on Bonny Oaks Drive as crews transition work zones between SR-153 and Chickamauga Avenue. Motorists should reduce speed and be prepared to stop. Signage and flaggers will be present, 03/23/23 through 03/30/23 from 9 AM - 1:00 PM. [2022-647]

 

HAMILTON COUNTY SR-317 (Apison Pike) improvement project from SR-321 (Ooltewah-Ringgold Road) to east of Layton Lane: Lane closures and flagging operations will be required on SR-317, Apison Pike, for utility and grading work. The flagging operations will be performed on 03/23/23, 03/24/23, 03/27/23, 03/28/23, and 03/29/23 from 7 AM to 1 PM and 3 PM to 7 PM. Closures will last about 2 hours per location. The contractor will have intermittent flagging operations during daytime non-peak hours for utility work, delivery of materials and equipment. There will also be flagging operations along Spalding Dr for the construction of Bridge 1.

[Wright Brothers Construction Company, Inc./Osbonlighter/CNT336]

 

HAMILTON COUNTY SR-8 (E. MAIN ST.) Utility Work both directions at LM 7.58: Interior lane closure between Jefferson Street and Madison Street. Motorists should reduce speed and use caution while traveling through the work zone and be aware of construction personnel. Trucks, signage, barrels/cones, and flaggers will be present, 03/13/23 through 03/29/23 from 9 am – 2 pm. [2023-062]

 

HAMILTON COUNTY SR-8 (E. MAIN ST.) Utility Work both directions from LM 6.39 to LM 6.42: Interior lane closure between S. Willow Street and S. Hickory Street. Motorists should reduce speed and use caution while traveling through the work zone and be aware of construction personnel. Trucks, signage, barrels/cones, and flaggers will be present, 03/27/23 through 03/29/23 from 7 am – 2 pm. [2019-543]

 

HAMILTON COUNTY SR-8 (E. MAIN ST.) Utility Work eastbound from LM 5.94 to LM 6.38: Shoulder and single lane closures from S. Orchard Knob Ave and S. Watkins Street. Motorists should reduce speed and be prepared to stop. Trucks, signage, and barrels will be present, 12/01/22 through 03/31/23 from 9 am - 2 pm. [2022-754]

 

HAMILTON COUNTY SR-8 (US-127) construction near Palisades Road (LM 15.2) to near Sunset Drive (LM 15.4): The contractor has closed the right lane going up the Signal Mountain Road from LM 15 (about 1/2 Mi from Palisades Road) to past Sunset Drive. This closure will be in effect for several months during the duration of this project. There will be intermittent lane closures on Signal Mountain Road as the contractor will have flaggers out as they work. Due to the possibility of flaggers stopping traffic, traffic should be aware of possible delays in this area.

[Wright Brothers Construction Company, Inc./Curtis/CNW001]

 

HAMILTON COUNTY SR-8 (US-41, US-76) Bachman Tubes cleaning: On Thursday Night of this reporting period, the contractor will be shutting down the tunnels from 8 PM-6 AM to clean it. There will be a signed detour for traffic to follow to get around the closure.

[Diamond Specialized, Inc./Curtis/CNW197]

 

MCMINN COUNTY SR-163 bridge repair over Chestuee Creek (LM 11.7): During this reporting period, the contractor will continue bridge repairs on the bridge over Chestuee Creek. Traffic on the bridge over Chestuee Creek on SR-163 at LM 11.74 will be reduced to a single lane controlled by a traffic signal. Maximum horizontal clearance will be limited to 11’. Wide load detour routes will be posted. Motorists are advised to reduce speed in the work zone. RESTRICTIONS: Maximum horizontal clearance 11 feet.

[Jamison Construction, LLC/Wagner/CNW282]

 

MCMINN COUNTY SR-2 (CONGRESS PKWY.) Utility Work westbound from LM 12.93 to LM 12.1: Mobile shoulder closure along SR-2 between the intersection of Congress Pkwy and Dennis Street and the intersection of Congress Pkwy and Rocky Mount Road. Motorists should reduce speed and be prepared to stop. Trucks, signage, cones, and flaggers will be present, 08/15/22 through 04/12/23 from 7:30 am – 5:00 pm. [2022-019]

 

MEIGS COUNTY SR-58 (STATE HWY. 58) Utility Work southbound from LM 14.22 to LM 9.35: Mobile shoulder and single lane closures from Goodfield Road to Cottonport Road. Motorists should reduce speed and be prepared to stop. Trucks, signage, cones, and flaggers will be present, 01/26/23 through 03/31/23 from 9 am – 2 pm. [2022-366]

 

RHEA COUNTY SR-30 (STATE HWY. 30) Utility Work eastbound from LM 13.01 to LM 16.37: Mobile shoulder and lane closures on SR-30 as crews transition work zones between Sky Drive and SR-302. Motorists should reduce speed and be prepared to stop. Signage and flaggers will be present, 03/23/23 through 03/29/23 from 9 AM - 2:00 PM. [2023-125]

 

RHEA COUNTY SR-302 (OLD DIXIE HWY.) Utility Work both directions from LM 0.01 to LM 2.5: Mobile shoulder and lane closures on SR-302 as crews transition work zones between SR-30 and Taylor Road. Motorists should reduce speed and be prepared to stop. Signage and flaggers will be present, 10/06/22 through 03/29/23 from 9 AM - 2:30 PM. [2022-643]

Happenings
Weekly Road Construction Report
  • 4/19/2024

Here is the weekly road construction report for District 29: BRADLEY COUNTY I-75 at Paul Huff Parkway Interchange modifications: During this reporting period, the contractor will ... more

“GO LIVE” Summer Media Teen Camp Returns
“GO LIVE” Summer Media Teen Camp Returns
  • 4/19/2024

The City of Chattanooga’s Department of Community Development has partnered with Dynamo Studios to host the “GO LIVE” Summer Media Teen Camp, where participants can express their creativity and ... more

Crabtree Farms Plant Sale, Sculpture In The Sky Set This Weekend
  • 4/18/2024

Two annual springtime events will be taking place this weekend in Chattanooga. Crabtree Farms Plant Sale will be on Friday through Sunday from 9 a.m. until 3 p.m. each day. On Friday and Sunday, ... more