Beam Problem Delays Opening Of 2 Bridges Near I-24/I-75 Split By 6 Months

  • Thursday, July 11, 2024

Tennessee Department of Transportation (TDOT) contract crews have revised their construction schedule for the S. Moore Road and McBrien Road bridges over I-24. This work is part of Phase II (the second of two projects) to widen and improve the I-75 at I-24 interchange.

Both bridges are expected to reopen in January 2025, six months later than expected.

Officials said, "The new timeline is a direct result of five new bridge beams being refabricated, at TDOT’s request, to adhere to the standards and specifications defined in the contract. TDOT has a rigorous quality control process for all materials. The five new beams were delivered and set this week. Phase II of the project is 40 percent complete and the estimated completion date for the entire project, in late 2025, remains unchanged as does the $161 million cost.

"Closing both bridges at one time allows for expedited construction of the bridges. Even with the delay, the traffic impacts are still reduced by six months to a year. Drivers are encouraged to reduce their speed through the work zone, follow posted signage, and remain alert to changing traffic conditions."

Additional information and resources (including detailed directions for navigating the bridge closures) can be found on the project’s website: https://www.tn.gov/tdot/projects/region-2/i-75-interchange-at-i-24-phase2/project-library.html

Breaking News
Updated City Tree Ordinance Allows "Notable Trees" To Come Off The List At Owner's Request
  • 4/1/2025

An amended version of the city's updated tree ordinance allows owners of "Notable Trees" to have them taken off the list by notifying the city forester. Chris Anderson of the mayor's office, ... more

Latest Hamilton County Arrest Report
  • 4/1/2025

Here is the latest Hamilton County arrest report. (If your case is dismissed, just email us your name and date we ran it and we will promptly take off. Email to news@chattanoogan.com ) BELL,TERRY ... more

Tennessee Adds Saturday REAL ID Appointments Ahead Of Federal Implementation Date
  • 3/31/2025

With the federal REAL ID travel requirement taking effect on May 7, the Tennessee Department of Safety and Homeland Security will open 19 Driver Services Centers across the state on Saturday ... more